We are highly committed to customer satisfaction.
R&D CENTER
Certification authority | KOITA (Korea Industrial Technology Association) |
Date of establishment | September 16, 2014 |
Major Study |
- Development of new parts (automobiles and windows, etc.), Testing and Analysis - Long-term technical development, process improvement research, business strategy research |
Professional Study |
- Improvement of Close-Proof (Weather strip, Sealing, Packing, etc.) - Process Development and Processing of New Materials - Design and development of ALL Rubber parts (Color coating, Joint, Adhesion, etc.) |
A road map for development of new techniques and methods
Phased advance verification
Automobile | Schedule | M+1 ~ M+6 | M+11.5 | M+13.5 | M+15.5 | M+17.5 | M+18 |
Development stage |
Prototype | M/Car | P1 | P2 | M | SOP | |
Quality check | First step Improvement / verification |
Second step Improvement / verification |
First step Improvement / verification |
Second step Improvement / verification |
ISIR approval Improvement |
Initial samples in preparation for mass production |
|
Industrial purposes |
Schedule | D+2 | D+5 | D+8 | D+12 | D+19 | D+25 |
Development stage |
Start | Review | Make molds | Make porotypes | Change designs (at customer's requests) |
Produce initial samples in preparation for mass production |
|
Quality check | Drawing receipt |
Drawing approval |
Inspection | Evaluation /Confirmation |
Improvement | Initial samples |
Prototype Stage
P1 Stage
P2 Stage